▪ Crews have begun paving between Blazer Plastics and 8200 South. This work is expected to continue though the middle of next week. Once the shoulder pavement is completed, crews will begin to pave driveway approaches from the shoulder to the property line.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills will begin in about a week.
▪
Crews have begun paving between Blazer Plastics and 8200 South. This work is expected to continue though the middle of next week. Once the shoulder pavement is completed, crews will begin to pave driveway approaches from the shoulder to the property line.
▪
Excavation of the shoulder, and placement of road base and pipe, south of Pettingills will begin in about a week.
▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪
The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪ Once paving is complete road paint and signs will be placed.
▪ Work in front of Pettingills is expected to begin in a few weeks.
▪
Once paving is complete road paint and signs will be placed.
▪
Work in front of Pettingills is expected to begin in a few weeks.
UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.
This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.
▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete the end of October 2017.
▪
Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪
Anticipate construction noise and vibrations.
▪
The right travel lane will be closed in the areas in which crews are working.
▪
This project is expected to be complete the end of October 2017.