US 89 Shoulders Project - April 19, 2017

Thursday, April 20, 2017 - 10:45am
UDOT

US 89 Shoulders Project - April 19, 2017

 

Current Work

▪ Crews anticipate paving the shoulders on the west side of the street beginning next week. This work will continue through the week.
▪ Questar Gas began installing a new gas line on the east side of the road. This work involves digging trenches along the east side of the road to place the new gas line.

Please do not move traffic control barrels or cones. These are placed in specific areas to insure the safety of motorists, residents, and construction workers.

Current Closures

▪ The southbound right travel lane is currently closed in the areas the crews are working. Due to the nature of the work, closures will vary daily.
▪ Temporary lane closures in the northbound right travel lane are expected over the next few weeks. This will be to accommodate work Questar is doing on the current gas line.
 

 

Upcoming Work

▪ Utility work on the east side of the road will continue through June.
▪ Excavation of the shoulders on the east side of the street is anticipated to begin in July.
 

 

Project Location

UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.

Purpose of the Project

This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.

What to Expect

▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ Right travel lane will be closed in the areas crew are working.
▪ This project is expected to be complete around Labor Day Weekend 2017.
 

If you have questions, comments, or concerns please call or email,

Rosie Fullmer

800-278-4282

 