▪ Crews are continuing to work on the concrete waterway in various locations along the east side on the road. Once the concrete is placed, the concrete will need to fully cure before traffic will be allowed to drive across it. This curing process can take up to 28 days. Please do not leave impressions of any type in the concrete. Damaged concrete must be replaced, costing additional tax dollars to be spent.
▪ Pipe work in select locations will take place through August.
▪ Excavation and placement of road bace is ongoing throughout the entire east side of the project.
▪
Crews are continuing to work on the concrete waterway in various locations along the east side on the road. Once the concrete is placed, the concrete will need to fully cure before traffic will be allowed to drive across it. This curing process can take up to 28 days. Please do not leave impressions of any type in the concrete. Damaged concrete must be replaced, costing additional tax dollars to be spent.
▪
Pipe work in select locations will take place through August.
▪
Excavation and placement of road bace is ongoing throughout the entire east side of the project.
▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪
The right lane for northbound traffic is closed while crews work on shoulder reconstruction.
▪ Crews plan to pave the shoulders on the east side of the road mid-to-late-Semtember.
▪
Crews plan to pave the shoulders on the east side of the road mid-to-late-Semtember.
UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.
This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.
▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete around Labor Day weekend 2017.
▪
Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪
Anticipate construction noise and vibrations.
▪
The right travel lane will be closed in the areas in which crews are working.
▪
This project is expected to be complete around Labor Day weekend 2017