Error message

UPCOMING CONSTRUCTION ACTIVITIES...1100 South

Wednesday, May 28, 2014 - 11:00am

BC Resident:
In an effort to keep you informed on the UDOT construction project the following information if being forwarded to you:

UPCOMING CONSTRUCTION ACTIVITIES...

May 27-28: Crews will close one lane of northbound I-15 during the day while they deliver piles for the bridge foundation.
May: Crews will pour footings, drive piles for the footings and form new columns for the south bridge of the 1100 South Diverging Diamond Interchange (DDI). Flaggers will assist in directing traffic on the 1100 South bridge during this work.
PROJECT INFORMATION
Work will generally take place from 7 a.m. to 6 p.m. Monday through Friday with occasional night and weekend work. Work activities and schedules are subject to change
Questions may be referred to the Public Works Administrative Offices by dialing 435-734-6615.