Error message

US 89 Shoulders Project Update 20

Thursday, August 3, 2017 - 10:30am
UDOT

US 89 Shoulders Project - August 2, 2017

 

Current Work

▪ Crews will continue excavation of the shoulders on the east side of the road. This work is expected to take another week.
▪ Piperwork in select locations will take place through August.
▪ A concrete water way will be placed on the north end of the project. This work is anticipated to begin next week.

Crews will continue excavation of the shoulders on the east side of the road. This work is expected to take another week.

Piperwork in select locations will take place through August.

A concrete water way will be placed on the north end of the project. This work is anticipated to begin next week.

Please do not move traffic control barrels or cones. These are placed in specific areas to insure the safety of motorists, residents, and construction workers.

Current Closures

▪ The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

The right lane for northbound traffic is closed while crews work on shoulder reconstruction.

 

Upcoming Work

▪ Crews plan to place concrete valley gutters in various locations along the east side of the road. This work is expected to take place mid-August. Once the concrete is placed, the concrete will need to fully cure before traffic will be allowed to drive across the concrete. This curing process can take up to 28 days.

Crews plan to place concrete valley gutters in various locations along the east side of the road. This work is expected to take place mid-August. Once the concrete is placed, the concrete will need to fully cure before traffic will be allowed to drive across the concrete. This curing process can take up to 28 days.

 

Project Location

UDOT is widening the shoulders on Main Street (US-89). This work is taking place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.

Purpose of the Project

This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.

What to Expect

▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ The right travel lane will be closed in the areas in which crews are working.
▪ This project is expected to be complete around Labor Day weekend 2017.

Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.

Anticipate construction noise and vibrations.

The right travel lane will be closed in the areas in which crews are working.

This project is expected to be complete around Labor Day weekend 2017.

If you have questions, comments, or concerns please call or email,

Rosie Fullmer

 

Tags: