▪ Excavation of the shoulders on the west side of the road is complete.
▪ Crews are currently placing new road base materials in the shoulder.
▪ Utility upgrades are taking place on both sides of the road.
▪ Questar Gas anticipates beginning some work next week. Some lane closures in the northbound right lane will take place in the areas that they are working in.
▪ The southbound right travel lane is currently closed in the areas the crews are working. Due to the nature of the work, closures will vary daily.
▪ Temporary lane closures in the northbound right travel lane are expected over the next few weeks. This will be to accommodate work Questar is doing on the current gas line.
▪ Questar Gas is expected to begin installing new gas line on the east side of the road beginning in mid-April. They will be digging trenches along the east side of the road to complete this work.
▪ Paving of the shoulders on the west side of the road is expected to take place the third week of April.
UDOT will widen the shoulders on Main Street (US-89). This work will take place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.
This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.
▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ Right travel lane will be closed in the areas crew are working.
▪ This project is expected to be complete around Labor Day Weekend 2017.
▪ Excavation of the shoulders on the west side of the road is complete.
▪ Crews are currently placing new road base materials in the shoulder.
▪ Utility upgrades are taking place on both sides of the road.
▪ Questar Gas anticipates beginning some work next week. Some lane closures in the northbound right lane will take place in the areas that they are working in.
▪ The southbound right travel lane is currently closed in the areas the crews are working. Due to the nature of the work, closures will vary daily.
▪ Temporary lane closures in the northbound right travel lane are expected over the next few weeks. This will be to accommodate work Questar is doing on the current gas line.
▪ Questar Gas is expected to begin installing new gas line on the east side of the road beginning in mid-April. They will be digging trenches along the east side of the road to complete this work.
▪ Paving of the shoulders on the west side of the road is expected to take place the third week of April.
UDOT will widen the shoulders on Main Street (US-89). This work will take place along US-89 in Willard starting near mile post 426 and extending almost to the junction of SR-126 and US-89.
This project will improve safety for those traveling by automobile and bicycle, by providing a paved standard shoulder in places that now only have a gravel shoulder.
▪ Work will normally occur Monday through Friday from 7 a.m. to 5 p.m.
▪ Anticipate construction noise and vibrations.
▪ Right travel lane will be closed in the areas crew are working.
▪ This project is expected to be complete around Labor Day Weekend 2017.