US 89 Shoulders Project Update 27

US 89 Shoulders Project - September 21, 2017

 

Current Work

▪ Crews have completed shoulder paving between Blazer Plastics and 8200 South.
▪ Crews plan to begin to pave driveway approaches, tomorrow. This work is expected to take approximately 1 week.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills is expected to begin next week.

Crews have completed shoulder paving between Blazer Plastics and 8200 South.

Box Elder Schools

Willard Updates September

Box Elder Schools

Box Elder Schools

US 89 Shoulders Project - September 14, 2017

Current Work

▪ Crews have begun paving between Blazer Plastics and 8200 South. This work is expected to continue though the middle of next week. Once the shoulder pavement is completed, crews will begin to pave driveway approaches from the shoulder to the property line.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills will begin in about a week.

US 89 Shoulders Project - September 14, 2017

Current Work

▪ Crews have begun paving between Blazer Plastics and 8200 South. This work is expected to continue though the middle of next week. Once the shoulder pavement is completed, crews will begin to pave driveway approaches from the shoulder to the property line.
▪ Excavation of the shoulder, and placement of road base and pipe, south of Pettingills will begin in about a week.

Box Elder School District Board of Education Board Meeting Minutes

Box Elder Schools

Willard City/ South Willard September Updates

Willard had a bit of a scare when testing results at the Willard School came back high for lead. New tests were conducted and it is good news.