With School starting in Perry, we would like to remind everyone to go slow and watch for children walking to and from school. Also, beware of school buses pulling off the highway and back on. There were several times cars went around busses stopped with flashing light at the end of the year last year. As always, we need to watch for all hidden dangers while driving.
The land dispute with Perry City and the Nelson Family was resolved regarding the land dispute without the need of further court action. The Mayor and City Council members hope this agreement will help the community heal and that all residents will come together to continue to make Perry City the perfect place to call home.
Save the Date!!! Oct 5th & 6th from 6 to 8pm, Perry City will be hosting a 2 night event to get input from the community members regarding a 10-year General Plan, planning for the growth and development of Perry City.
Geneva Rock had early operations during the month of August starting on the 9th. In support of the I-15 three lane expansion project Geneva Rock will be starting operations at 3:00 a.m. This was coordinated through the Mayor and Geneva rock. We apologize for any inconvenience this may cause.
I-15: Box Elder Project Corridor Activities
Day and nighttime construction activities are expected in all areas, speed limit: 65 MPH along the construction corridor. Items being done are clear, grub, excavation, backfill, barrier, storm drain activities, fencing, sign relocation, paint and tape removal and asphalt and concrete paving.
Bridge and utility work continue along the construction corridor with intermittent, nighttime, single lane configuration. I-15: New Traffic Configuration: Northbound, August 19 – Southbound, August 21 Construction crews project a traffic pattern shift to the new concrete pavement, in order for the outer auxiliary lanes to be constructed.
I-15: Ongoing Corridor Activities Farr West – Brigham are single lane closures: Bridge and Paving Activities, bridge work, paint/tape removal and concrete paving along the construction corridor through fall 2016. Intermittent, nightly, single lane configurations in 3 mile segments
I-15: Farr West to Brigham City - Bridge Work Continues
Bridge work continues along the I-15: Box Elder corridor with day and nighttime activities expected to take place in your area. Motorists and residents may experience an increase in noise, light, dust, vibration, construction personnel, vehicles and machinery in the area.
I-15 Bridge: 2950 South - Perry
Bridge demolition at the I-15, 2950 South Bridge is projected to take place next week
Closure/Work Schedule August 22 – 24: 2950 South is projected to be closed to motorists traveling east and west under the bridge with intermittent, single lane configurations north and southbound will take place on I-15 near the 2950 South Bridge. Detour Route: 2700 South.
I-15 Bridge: 750 North - Willard
Bridge demolition at the I-15, 750 North Bridge is projected to take place next week Work Schedule - August 24 – 26. A flagger may be onsite to direct traffic. Intermittent single lane traffic for motorists traveling east and west under the bridge, intermittent single lane configurations north and southbound will take place on I-15 near the 750 North Bridge. Detour Route: US 89.
I-15 Bridge: 7800 South - Willard
Bridge work at 7800 South is projected to continue through fall 2016. Motorists traveling east and west under the bridge may encounter intermittent lane restrictions. Daytime and nighttime activities may take place. Detour Route: 8700 South – 1500 West.
I-15 Bridge: 8700 South - Willard
Bridge work at 8700 South is projected to continue through fall 2016. Motorists traveling east and west under the bridge may encounter intermittent lane restrictions. Daytime and nighttime activities may take place. Detour Route: 7800 South – 1500 West
I-15: Perry Rest Area
Utility work and concrete paving is scheduled to continue at the northbound Perry Rest Area through fall 2016. The Rest Area will remain open with limited parking available.
Construction schedules are subject to change due to weather, equipment or material delays.
Safety Reminder
For your safety and the safety of those working in the area, please exercise caution, stay alert and be prepared for changing lane configurations throughout the construction corridor.